Earned value for construction contracts
![]() |
Earned value analysis (EVA), also known as earned value management (EVM), is a technique used to assess project progress by comparing the amount and cost of work that was planned to have been done by a particular stage with the amount that has actually been done and what it has actually cost.
This gives a good indication of how the project is progressing compared to what was planned and enables forecasts to be made about the eventual cost and time that will be required to complete the project.
Typically, EVA is carried out for each of the packages that make up the project. Actual outputs are measured against planned outputs (often on a weekly basis) using the units that individual companies use to price and measure work.
This provides an opportunity to investigate discrepancies and take remedial action where necessary. It also provides a fairly accurate insight into the financial wellbeing of package contractors and provides early warning of a shortage of resources or of an inefficient use of resources.
The key is to measure actual resource against planned resource using the production units by which estimates have been produced in order to price a tender. This can be:
- Hours worked per week.
- Number of workers per week.
- Volume of say, concrete per week per person.
- Units fixed per week per person.
These items can be plotted weekly to alert the user to trends and allow them to investigate causes. Furthermore, it provides an overall general picture of labour productivity for each monitored operation.
Carrying out this sort of analysis requires that project planning is broken down into packages and that tender documentation is drafted to require contractors to supply the information required.
[edit] Related articles on Designing Buildings Wiki
- Benchmarking.
- Contractor.
- Cost monitoring.
- Cost performance index (CPI).
- Identifying the causes of trends in construction labour productivity.
- Key performance indicators.
- Programme consultant.
- Progress of construction works.
- Schedule performance index (SPI).
- Sub-contractor.
- Tender.
- Tender documentation.
[edit] External references
Featured articles and news
A threat to the creativity that makes London special.
How can digital twins boost profitability within construction?
A brief description of a smart construction dashboard, collecting as-built data, as a s site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.